A SUMMARY AND OBSERVATIONS
Not in any particular order but numbered for ease of
identification.
All links will open in a separate window which
will need closing |
Do feel free to read all
of the following, but because there are so many paragraphs I have also
made this list with links, for you to cherry pick what takes your fancy:
|
| << Return
to home page of this Eagry web site |
1. EXISTING PROPERTIES OMITTED. Not
a single plan submitted to the Planners carried the location of the
twenty Eagry
houses which border the site. (With the exception of two houses).
So even now,
fourten months after the plans were approved, we are not sure
what is to be built behind us and what it's position is. Surely we
have
a right to know this information. At
least two of the Planners' own guidelines booklets state that locations
of existing abutting dwellings should be shown.Yet
the planners never asked for this and what's more we were told by the then
Divisional Planning Manager that it was unnecessary
We
say the law needs changing to insist developers use up-to-date location maps
and which also show adjacent properties. (See Plans page)
On 11th September 2004 we wrote to the Divisional Planning
Manager asking .... 'why
your department did not insist that all the existing Eagry properties
which bound the southern edge of the site, be shown on the plans?'
When she did not
answer we wrote to the Chief Executive asking the same question. Three
months after the initial query we received the following
reply which was endorsed by the Planning Secretariat.
This is a paraphrase of the lady's reply. The full correspondence can
be seen in the Public Application Files at the Coleraine Planning Sub-Division
"There is no requirement
to show position of dwellings on adjacent lands".
DIVISIONAL
PLANNING MANAGER 13 Dec.2004 |
I have replied as follows:
| "From your reply it
would appear planners need a “requirement” to
hide behind, rather than taking pity on and informing neighbours
of the position of their property in relation to this new development
of 2 storey dwellings which will overshadow and loom over their
existing bungalows?" |

|
2. BUILDING ON FLOODPLAIN. 18
th November 2003, Rivers Agency advised Planning Service "against
permitting development in floodplains or the in-filling of floodplains
to facilitate
development". (They
even included a large scale map defining the area) Yet that same department,
in the same letter, in the same paragraph, accepted infilling
encroaching,
in
places
by more
than
75%,
into the
very 100 year
flood area which they defined. (See Flooding Pages)
And way back in August 2001, referring to the original plan, Rivers
Agency wrote to the Planners
"Rivers Agency
is opposed to any infilling for
development purposes, in areas of flood pondage, as the resultant displacement
of flood water can cause problems elsewhere within the catchment."
On
11th September 2004 we wrote to the Divisional Planning Manager asking' ....Why
was the nonsensical paragraph from Rivers Agency included in the
Decision Notices Informatives and
not
queried with them and resolved before getting to this stage? And what
advice will you be giving to the Enforcement Officer once construction
work starts within the above ‘no-build’ zone? ‘Ignore
the Decision Notice’? In which case why have a Decision Notice?'
When she did not
answer we wrote to the Chief Executive asking the same question. Three
months after the initial query we received the following
reply which was endorsed by the Planning Secretariat.
This is a paraphrase of the lady's reply. The full correspondence can
be seen in the Public Application Files at the Coleraine Planning Sub-Division
"A/. This was an informative
and “people
buying a dwelling and their solicitors will wish to satisfy themselves
that the prescribed levels have been adhered to”.
B/. “Rivers
Agency addressed the issues relating to flood-plain in their letter
to you 9th March 2004”
Enforcement will not be required … Enforcement
action cannot be taken on Informatives."
DIVISIONAL PLANNING
MANAGER 13 Dec.2004 |
I have replied as follows:
"You
did not answer the question “Why did you not query…..?”
Well at least I queried this contradictory Rivers Agency statement.
Which is more than Planners apparently did.
A/. Writing (21-5-02) about an earlier version of this plan,
a member of the Rivers Agency, said “Rivers Agency has made the Planning Authority aware
that flooding can occur adjacent to the Distillery Burn… It is a matter
for the Planning Authority to approve any development at this location”.
Now here you [Divisional Planning Manager] are, saying it is up to the Solicitor
and prospective purchaser to satisfy themselves the prescribed levels have
been adhered to. Is no-one willing to accept responsibility anymore?
B/. Twice I wrote to the Rivers Agency - 16 Feb 2004 to the
Chief Executive and again 22 March 2004 to the Director of Operations.
I wrote to the Dir of Ops. as I was not satisfied with the Chief
Exec.'s earlier answer - the answer that you quoted as sent to
me on 9th March 04 and which
you say “addressed “ the issue. ‘Addressed’ but certainly
not answered to my satisfaction. If Planners meekly accept such ambiguity I
will not.
By insisting on clarification from the Rivers Agency, the planners
could have averted the disappointment when prospective purchasers
of four of these dwellings discover their new homes are partly in
a known floodplain. " (NEW - See
photo album of flooding which occured on 12 March 2006. Opens
in separate window) |
 |
"It hasn’t gone
away you know.
Above photo taken 8th Jan 05. Site 0247 in foreground. I note
Angela Smith (Minister for the Environment) is asking for comment
on the “Consultation
Draft PPS 15 – Planning and Flood Risk”. I will, of course, be
sending her all the relevant correspondence associated with this particular
flood plain
fiasco.
["Enforcement action cannot
be taken on informatives"] At least this absolves enforcement
officers when the road/dwellings are flooded or subsidence takes
place and the inevitable enquiry ensues." |
 |
3. NON-ADVERTISED PLAN ACCEPTED.
Several agencies referred to the drawing dated 28th May 2003 (Drg 02/55:22)
as the "final layout".
We were confused as this was not the last plan advertised in the local
Press
which was
the July
2002
version. So we queried this (18th March 2004) with
the Divisional Planning Manager asking what Layout Plan/Drawing number
was finally approved by Planning Service and taken to Moyle Council
in November 2003? . We have subsequently received a reply (7/4/04) stating
the approved plan was drawing no. 02/55:02 (30th May 2003). But
this layout has never appeared in the local press Planning Applications.
Compared
to the previous plan, - of the 26 dwellings which directly abut onto
the established Eagry dwellings, 21 of them have been changed (Four
moved further
away and 17 moved nearer- up to one third nearer in some cases) There
are many other changes too, so see Differ page
to compare the differences.
We sent a comprehensive list of these differences, together with a drawing
showing the two plans superimposed, to the Divisional Planning Manager
on 18th April 2004. But after a month had passed without
even an acknowledgement we sent another copy of the same documents to
the Manager again, on 18th May 2004 (only this time to be “signed
for on delivery”). We then had a speedy reply apologising for not
acknowledging our first letter. And noting that the points raised “will
be fully considered before any decision is issued on these applications” That’s
an ambiguous statement and does not necessarily mean they are even considering
our request for the plan to be advertised. On 29th
June 2004 the "Decision Notices" were issued giving the
go-ahead to this unpublished plan. What's the word used to describe
an event when two parties proceed with a plan without telling the
third party who is also involved?
- Duplicity? Collusion? On 11th September 2004 we wrote to the Divisional Planning Manager asking
..... 'why the Amended Plan
(Drawing No. 02 received 30/5/03) was not advertised in the local press?'
When she did not
answer we wrote to the Chief Executive asking the same question. Three
months after the initial query we received the following
reply which was endorsed by the Planning Secretariat.
This is a paraphrase of the lady's reply. The full correspondence can
be seen in the Public Application Files at the Coleraine Planning Sub-Division
"In this case the plans
addressed issues of detail required to ensure a quality residential
development….
All files are open to the public therefore nothing is secret"
DIVISIONAL PLANNING MANAGER 13 Dec.2004 |
I have replied as follows:
"Detail? Seventeen
dwellings moved; two house types changed; a road moved
11m into and
along important wetland; and two dwellings omitted … and
you call all these changes mere detail?
All these amendments are accepted by Planning and yet you
put the onus on the “objectors” to
find out by constantly visiting the files in Coleraine just in case amendments
are made which planners aren’t publicising. This is totally irresponsible.
But then that’s how you also treated the Environmental Heritage Agency
(See 21).
What timescale and how often do you
recommend objectors should monitor the Files?"
RESPONSE FROM PLANNERS 18th March 05
"It is for the objector(s)
to make a judgement as to the frequency with which they should or
would wish to view application files"! |
 |
4. NON ADVERTISED PUBLIC ENQUIRY. A
Public Enquiry was held to discuss proposed new housing developments
in the
Bushmills
area. Although deeply affected
by one such
proposal,
Eagry residents were not informed of this event, even though objectors
to another
development were sent individual invitations. Although billed as a "public" enquiry
we are unaware of any advertising in the local press. (See
Public Enquiry page)
 |
5. CONSTRUCTION TRAFFIC. Residents are
concerned that the heavy construction traffic will use the narrow, steep
Eagry Park
road to get to the new
site. Road's
Service answer to their worries was summed up in one sentence..." common
sense would tell one that if a housing development is to be extended
there will be construction traffic using the existing road“ (See
Site Traffic page) The developers have now been
given approval for a temporary site entrance directly off the Straid
Road. But this
is only for two
years so the top site traffic (0247) might still use Eagry.  |
6. OVERDEVELOPMENT. The first amended plan was refused as it was "...contrary
to Planning Policy Statement 7 : Quality Residential Environments'
- Overdevelopment". Yet that plan did not even show the
house types. (See Visual
Impact page) They could have been one-bedroomed
huts or six storeys high flats for all the Planners knew.
 |
7.HOUSE MIX. The original, refused, proposal showed
a mixture of two storey houses and bungalows on the skyline at different
angles to each
other
and painted
white. But the approved plan shows a 'wall' consisting of a straight
row of terraces and two-storey houses, one of the terraces having dark
grey
exterior walls. Is that visually more attractive? (See Visual
Impact page)
 |
8. STANDARD HOUSES. In
a note which accompanied the original plan, a member of the Planning
Development team wrote ..."There
is a continued use of standard house-types, which have featured widely
in
other locations".
There were twenty six of house type MD41 in the original proposed plan.
Planning Service has now approved the latest layout, which includes twenty
four type MD41. Just two less. And I have not even included the mid-terraced
houses
which have several more of these MD41 types lumped together. (See Visual
Impact page) And the developer has even attempted to add another
set of MD41's But building of this pair has appears to have ceased after
Enforcement issued a warning letter. CLICK
to see this wrong building
On 11th September 2004 we wrote to the Divisional Planning Manager asking
' ...... Why were these plans
accepted which show a continued use of existing house types?'
When she did not
answer we wrote to the Chief Executive asking the same question. Three
months after the initial query we received the following
reply which was endorsed by the Planning Secretariat.
This is a paraphrase of the lady's reply. The full correspondence can
be seen in the Public Application Files at the Coleraine Planning Sub-Division
"It is not unusual to re-use the same house
types. The comment made by the original Case Officer was not a complaint
more an observation."
DIVISIONAL PLANNING MANAGER 13 Dec.2004 |
I have replied as follows:
"CREATING PLACES 3.32 states: “An
even distribution throughout the layout of developers’ standard
ranges of dwelling designs should be avoided”.
But you, Divisional Planning Manager, don’t acknowledge this statement.
(I expect you call this an “Observation”) In fact go as far as
to accept it as being ‘not unusual’.
But this was a Policy statement.
In my original letter to you I was not quoting the Case Officer – saying ‘there
is a continued use of standard house types used elsewhere’ - but a Senior
Professional and Technical Officer who was a member of your Development Team
writing to the Case officer on 23-7-01. and quoted by that
Case Officer after her site visit on 27-07-01, under her section “Assessment
of Policy”. But no matter who said it, I cannot see them bothering to
make this “observation” without inferring that this comment has
a bearing on the proposed development and that using the same house types is
bad design. Hence it coming under the Case Officer’s heading of “Assessment
of policy” |
|
9. TWO AND HALF HOUR TRAFFIC SURVEY. The
first amended plan was turned down because, amongst other reasons, there
was "unsatisfactory access" .
However as a result of a one
day traffic survey spread over two and a half hours this was
changed to being "acceptable". Surely such a paltry survey
is not worth the paper it's written on? The survey took place during
commuting hours
yet much of the present Eagry traffic, and no-doubt the extra new development
traffic as well, will consist of holiday makers who are not commuting. (See
Residential Traffic page)
|
10. WHAT'S TO BE BUILT? The plan was approved last November 2003. Construction
work started on the site on 16th Jan 2004. The Decision Notices were
issued
on 29th June 2003 yet the approved plan was never published,
so all we can do is look out of our back windows and watch the construction
work
progress
and
wonder
what
is to be built behind us?
(See Work
Started page)
 |
11. DEVELOPING ON WETLAND. Part
of the land scheduled for this development is wetland. "One
of the few wetland areas in North Antrim". In 1971, Governments
around the world signed up to to preserve wetlands. Yet here is development
and
in-filling on our very own rare wetland being allowed by Coleraine
Planning to take place. We say - "lip service", that's all
these conventions are when flouted in this manner. (See Trees
and plants section).
"Economic difficulties
of the Province have meant that there has tended to be a bias in favour
of the landowner
and developer, sometimes at the
expense of the environment" Parliamentary
Environment Committee report (Rossi) 1990 (Not much change there in 15 years!)

|
12. COUNCIL ACCEPTANCE How
do the Moyle Councillors view a new estate of 66 houses? - What is
their
most
important criteria when accepting a new development?
-----
12a. The look of the estate in this Area of Natural Beauty?
12b. As affordable housing for young members of the Bushmills community?
New terraced houses built by the same developer are on sale in
Bushmills for £110,000
and, according to their adverts, would be "....Ideal holiday
or investment homes"
12c. As more second homes?
12d. As more dwellings (no matter what standard and no matter for whom
they are aimed) which mean more rates to be paid by the new owners? (See Council page)

|
13. GLOBAL WARMING. In spite
of all the talk of global warming, flooding etc, here, in the year 2005,
is a development still being allowed to
go-ahead
and
build
on a flood plain (See Flooding page)
 |
14.COUNCIL AGENDA. On 24th November 2003, Moyle Council debated (well
actually there was no debate) and approved this planning application.
We (the
objectors)
were
not told this item was on the agenda so did not attend to hear our
Councillors represent us. Surely this meeting and what was to be discussed
should have
been advertised? We say
methods (not just the internet) need to be put in place to enable people
to know
what is coming up at the next Moyle Council meeting.(See Council page).
The Planning Service now posts a list of
Planning Applications coming up before Councils. CLICK
HERE to see it
|
15. CONSPICUOUS DWELLINGS. In the original proposal there were
2 x detached two-storey houses and 3 x bungalows on the highest part
of
the
site.
Now the latest
-and
accepted- plan shows those dwellings replaced by a two-storey
terrace of four dwellings and 2 x two-storey semi-detached houses. (The
bungalows have gone). Are we to presume that Planners are happier to
accept a two storey terrace instead of bungalows at the highest and
visually most noticeable
part of the development? (See Visual
Impact page)
 |
16. NECESSARY.Is this Development necessary?
Who wants sixty six new dwellings of this size and price in Bushmills?
Please reply to the contact
given
below.
According
to one
objector,
at one time it is believed there was "over 1,200 dwellings (apartments
etc) which cannot find owners in the North East" (See Needed page)

|
17. NOTIFICATION It is NOT a statuary requirement of Planners to issue
Neighbour Notifications. We
say this should be made law (See Work
Started page)
|
18. START WORK It is not illegal for a developer to
go on site and start work before Planning Permission is granted. We
say starting work on a site before obtaining written permission should
be made against the law.(See Work
Started page)
|
19.ENFORCEMENT We understand there are 22 enforcement officers for the
whole of Northern Ireland. We
say these need to be augmented. (See Enforcement page)
|
20. BUILD ON FLOODPLAIN. Builders can go ahead and
build on a flood plain and there is no way or law to stop them. Agencies
can only advise and
recommend
they
do not
build. We say the law needs
to be changed. (See Flooding page)
|
21. PUBLIC ALERTS EHS.
Six months after a plan is approved, one agency expresses serious
concerns
about
it!
On 6 November 2002 the Environment & Heritage Service,
(Natural Heritage) agency accepted the proposed development. And it
would appear, on the
basis of their acceptance (and the other agencies as well), the plan
was approved by the Planners in November 2003. But the plan EHS
was accepting had been superseded. We think they were unaware
of
this
new version, so wrote
to the Divisional Planning Officer asking that EHS Natural Heritage
be
given sight of the new (approved) plan. He replied .... "In
view of your queries, we will clarify any outstanding issues with EHS." This
EHS Agency
has now replied, thanking planning for the new documents, and saying
they have "serious
concerns with this amended proposal" and requesting
several amendments. ( See Trees page) It would appear it took our enquiry to kick start the
Planning Department to alert EHS to this amended plan. Draw
your own conclusions re the efficiency of the system.
On 11th September 2004 we wrote to the Divisional Planning Manager asking
why ... 'it
took ourselves, who are members of the public, to alert yourselves and
EHS to this important discrepancy?'
When she did not
answer we wrote to the Chief Executive asking the same question. Three
months after the initial query we received the following
reply which was endorsed by the Planning Secretariat.
This is a paraphrase of the lady's reply. The full correspondence can
be seen in the Public Application Files at the Coleraine Planning Sub-Division
| The Divisional Planning Manager did not reply
to this question |
I have replied as follows:
| "Considering an amended plan without alerting
one of the Agencies directly involved is a fundamental flaw in
your system. Instead
of ignoring my question (And your avoidance has been endorsed
by the Planning Secretariat), I suggest this misadministration
should be investigated to ensure this doesn't happen again." |
|
22 COUNTLESS GUIDELINES IGNORED. Over
the years the Planning Department has published many guidelines and policy
recommendations.
However the Coleraine Planning Department (and the developers) would
appear to have deliberately ignored many of these guidelines in
this proposed development. See Guidelines to
read several pages of ignored recommendations. Here's just one :- Several
Planning Guideline
documents
say that "Applicants
will be required, as a minimum, (to) provide a short written statement
setting out the design principles". However,
no written statement was ever supplied nor, more interestingly, ever
asked for, by the Planners.
And here's another:- "Developers
will need to demonstrate that their proposals will avoid significant
... overlooking and loss of privacy. CLICK TO
SEE PHOTO OF THE VERY FIRST BUILDING CONSTRUCTED!
We asked the Divisional Planning
Manager Who
decides which guidelines are to be adhered to and which ones to ignore?
"The final opinion is formulated by the Development
Control Group."
DIVISIONAL PLANNING MANAGER 13 Dec.2004 |
I have replied as follows:
"So it’s
not the fault of one person but a collective decision to ignore
guidelines?"
RESPONSE FROM PLANNERS 18th March 05 "The
Development Control Group consists of an Authorised Officer and
at least two other planning officers" |
|
23..DISARRAY The Planning Process is in disarray. On this web site you
will find examples of :-
Inefficiency. (EHS working to out-of-date plans)
Double speak (Rivers)
Terminological inexactitudes (That ignored "buffer" strip of
land)
Layouts misread (Heritage)
Plans misread (a four bedroomed house with only three bedrooms)
Dubious surveys (Roads)
Procrastination (5 weeks to even acknowledge a letter, three months to
answer it-Planning)
Procrastination (Plan Approved Nov 2003. Decision Notices finally issued
June 2004)
Overwhelmed staff (Planning)
Platitudes (Rivers SUDS)
Ignored environment (Building over wet lands)
Secrecy (Unpublished layout approved)
Deviousness (Existing properties omitted from plans)
Lessons ignored (Building over floodplain)
Policy guidelines totally ignored,
Plans stamped "approved" but not even read (only 3 beds in 4
bedroomed plan)
and a Council which apparently unanimously welcomes second homes.
 |
| 24. |
25. HEDGES. Under the Wildlife (NI)
Order 1985, it is an offence to damage or destroy the nest of any wild
bird whilst it is being used or built, or disturb any wild bird while on
or near a nest that is being built. And under Good Farming Practice the
trimming of hedges is not permitted from 1st March until 31st August. But
there appears to be somme confusion about weather the law applies to construction
workers. (in the case of this development hedges
have been ripped out during the nesting season) . This
Wildlife Order needs to be clarified.
|
26.EHS 'SERIOUS CONCERNS' CONSIDERED "UNREASONABLE" In
a letter (1st April 2004) to the Planning Service, EHS Natural Heritage
had .."serious
concerns with this amended proposal Here
is an extract from that letter:
| "..we
requested a 10m no development zone along the stream, which was
to have a planting belt of native species. We are concerned that
the drawings indicate proposed infill within the 10m corridor
and that fencing is proposed along the river edge. We request
amendments to the proposals to ensure that no infill,
development, fencing, ground disturbance or re-seeding takes
place within the 10m zone." [MY
EMPHASIS] |
Apart from omitting the fence, these requests have been totally
ignored and the planners have allowed infilling, development,
ground disturbance and reseeding, all to take place within the 10m
zone. There's a 80m (262 feet ) long road embankment to be built which
will run lengthwise within this zone. But this was meant to be a tree belt
and wildlife corridor.
On 11th September 2004 we wrote to the Divisional Planning Manager asking'
....why these concerns by EHS Natural Heritage were not addressed?'
When she did not answer we wrote to the Chief Executive
asking the same question. Three months after the initial query
we received the following reply which was endorsed by the Planning
Secretariat. This is a paraphrase of the lady's reply. The full correspondence
can be seen in the Public Application Files at the Coleraine Planning
Sub-Division
"The
amendments were accepted in their [EHS] letter July 2002 (Copy
enclosed) … but
EHS concerns in April 2004 that their requested 10m zone should
still apply
were considered
unreasonable". DIVISIONAL PLANNING MANAGER
13 Dec.2004 |
I have replied as follows:
| "You refer to EHS accepting
an amended plan in July 2002. I agree, they did, but that is the
whole point of my complaint. The plan (Drg.
04) to which they agreed was superseded in many respects after that,
and in the final accepted plan an embankment is to be built through,
along and within that zone. Yet you still held their year-out-of-date
acceptance as valid.
Your reply to me says a copy of EHS July 2002 letter is enclosed.
But it was not. I suspect because it contains the embarrassing
(to you) sentence…”The planting belt should be a minimum
width of 10m of locally native specimens of Alder and Willow"
To sum up;
On 19th February 2002, a year before the final amended plan was
accepted, EHS wrote the following to your department “…no
development should take place within 10m of the river and the
site layout should be redesigned accordingly.”
On 8th July 2002 EHS wrote, …”The planting belt
should be a minimum width of 10m of locally native specimens
of Alder
and Willow”
On 28th October 2002 EHS wrote, “ …A
wildlife corridor must be provided through the site. The
10m strip of trees along
the stream can accommodate this,”
On 1st April 2004 EHS wrote …”We
request amendments to the proposals to ensure that no
infill, development, fencing,
ground disturbance or re-seeding takes place within the 10m zone."
Yet after all the above pleadings over
the years, that request is deemed by the then Divisional Planning
Manager as “unreasonable”.
On 6th April 2004 his handwritten note reads as
follows ….
 |
I have reprinted it here because, even allowing for the
degredation by the web reproduction process, it is very hard
to decipher.
Which is a pity, considering what an important statement this
is. I have put a question mark against words I am uncertain
about.
"I am satisfied that following the lengthy
negotiations and agreements with the agents it would be unreasonable
to seek further amendments(?)
to the scheme which is in all other respects, entirely(?) satisfactory.
However a condition omitting the fence should be attached to the
approval".
(A Planning Officer confirmed the signature to
be that of the then Divisional Planning Manager)"
|

|
26a. A LAW TO FORCE A REPLY? At
the time of writing this paragraph (30/10/04), a public consultation paper
(Click for pdf copy)
has been published in which people are being asked to comment on “Proposals
to Amend Primary Planning Legislation in Northern Ireland”.
One of the questions posed is: - “Do you consider that … there
are any benefits in a legislative requirement for consultees to respond to
consultation requests within a specified timescale?”
What a reflection on the Civil Servants who run the various agencies - Water;
Rivers; Environmental Heritage etc. that Government is even considering a law
to force them to reply to Planners’ queries in a “specified time”?
Imagine if this happened in the private sector, say British Airways, and it
took a law to force one department to reply in a specified time to a request
from another?
Not that it matters, because when an agency does reply the Planners
ignore them (See Par 26 above)
|
26b. NO ACTION ON DECISION NOTICE ERRORS. The final
Decision Notices have several anomalies. Paragraph
10 for instance refers to the Landscape Plan drawing No
14 dated 13 February 2003. Whereas in actual fact this particular drawing
is of a house type and nothing to do with a landscape plan. CLICK
for more mistakes in the Decision Notices
On 11th September 2004 we wrote to the Divisional Planning Manager asking '...
Are Decision Notices legal documents? And if so, and errors are discovered,
does the Notice have to be withdrawn and a new one drawn up and issued?'
When she did not
answer we wrote to the Chief Executive asking the same question. Three
months after the initial query we received the following
reply which was endorsed by the Planning Secretariat.
This is a paraphrase of the lady's reply. The full correspondence can
be seen in the Public Application Files at the Coleraine Planning Sub-Division
The Divisional Planning Manager did not answer this question about
them being legal documents. Although in answer to another question
she did say ; "It's
a matter for the Courts to interpret a planning decision where
ambiguity occurs"
She went on to say “I accept there has been a number
of typographical errors…I am satisfied that the various conditions can
still be enforced”.
DIVISIONAL PLANNING MANAGER 13 Dec.2004 |
I have replied as follows:
"I cannot think of any reason why you
did not answer this simple question [Are Decision Notices legal
documents?]
except,
perhaps, that you don’t know the answer. However you’ll
be interested to know a lady representing the Planning Secretariat
wrote to say she had nothing further to add to your replies,
so I can only assume the Secretariat doesn’t know the answer
either.
I note you make no mention of amending the
Decision Notices. Yet in the “Reforming Planning. Public Consultation Paper
August 2004” the… “Department
proposes to introduce a legislative framework whereby simple
omissions or minor errors contained in Departmental planning
decision notices can be amended after decisions have been issued”
Why are they bothering to consider this when Coleraine Planning Sub-Division
appears to be content to let errors stand?" |
|
27. WRONG HOUSE TYPE BUILT. The very
first building has now reached the second floor of construction.
AND IT
IS NOT WHAT
WAS APPROVED by the Planning Decision Notice. What should be built
is a semi chalet type with no windows at the second storey but Velux
windows in the roof. What in fact has been built is a semi with windows
on the second storey which are looking straight down into the existing
Eagry Park bungalows, back rooms and gardens. The building is also
approximately three feet higher than approved. CLICK
for details
Update October 30, 2004 The Enforcement section
of the Sub-Divisional Planning Office (Coleraine) visited the site
and on 26th August 2004 issued "...a
warning letter advising the developer that a breach had occurred
and that they are proceeding at their own risk. ....As no response
has been received from the builder, the Department now intends
to send a final warning letter seeking compliance with the approved
plans." The top storey blocks have now been removed
and work has started on the "accepted" lower version
of this set of semis.
|
 |
28. MISSING BEDROOM. Drawing 08 received
5th November 2003 has been stamped “Approved”. It is a plan
and elevations of house type MD96 which, according to the main layout
drawing
02, is
a four bedroomed detached dwelling. But there are only three bedrooms
drawn. - Bedrooms 2,3 and 4. - Curiously no bedroom number one appears.
In fact there does not seem to be space to build a bedroom number one.
It can’t be that the developer is planning to offer the lounge
as an alternative bedroom because all the other house types with four
bedrooms all have lounges as well (Types MD86A and MD86 for instance).
On 11th September 2004 we wrote to the Divisional Planning Manager asking '.....Does
your department study plans and elevations of house types submitted
to them? Presumably so, otherwise they would not require them to be
sent in. And if they do, and find an irregularity, ie Type MD96, should
they not query it with the developer and ask for new plans to be
submitted?'
When she did not
answer we wrote to the Chief Executive asking the same question. Three
months after the initial query we received the following
reply which was endorsed by the Planning Secretariat.
This is a paraphrase of the lady's reply. The full correspondence can
be seen in the Public Application Files at the Coleraine Planning Sub-Division
"Planning Service require the submission
of house types for three purposes. To ensure a range of house
types; check footprint v site curtilage; ensure
elevation
detail
is
acceptable….The
type MD96 is a three bedroomed dwelling and not as you indicated".
DIVISIONAL PLANNING MANAGER 13 Dec.2004 |
I have replied as follows:
"Thanks for that information. Drawing
08 was obviously superseded with a different version, which I
did
not buy a copy of.
However if this is a three bedroomed dwelling why does the ‘Approved’ main
layout drawing (02/55:02 received 30th May 2003) show,
in it’s list of house types, that the five type MD96 dwellings are FOUR
bedroomed? From this ambiguity it would appear that the planners know more
about what the developer is to build than the developer himself?
If they build a four bedroomed dwelling but you say their plan shows only a
three bedroomed one, then I assume they will need to apply for a change of
house type
and you will have to advertise same. "
RESPONSE FROM PLANNERS 18th March 05 [In answer
to the above question 'Will they have to re-advertise?' ] "Yes"
(they will have to re-advertise) |

|
29. STORM PIPELINE. A note on Drawing
02 states “Each
dwelling shall be provided with a… 150mm dia. storm pipeline to
the public sewer” Yet the actual drawing shows a completely separate
storm pipeline running throughout the development and not connected to
the public sewer. This contradiction was not "picked up" by
the Planners and the drawing has subsequently been stamped "approved"
On 11th September 2004 we wrote to the Divisional Planning Manager asking '
.... how has your Department interpreted these apparently opposite
confusing instructions?'
When she did not
answer we wrote to the Chief Executive asking the same question. Three
months after the initial query we received the following
reply which was endorsed by the Planning Secretariat.
This is a paraphrase of the lady's reply. The full correspondence can
be seen in the Public Application Files at the Coleraine Planning Sub-Division
| The Divisional Planning Manager did not attempt to explain this
anomaly, instead said the Developer has to liaise with the Water
Service. |
I have replied as follows
| "So when drafting Decision Notices and Informatives
why bother using phrases such as “Should be carried out in
full” or “In
accordance with stamped approved“, when final decisions are
being made which must go against these set-in-stone drawings? I
suggest you drop these phrases if you don’t mean them. " |
 |
30. DISTILLERY FORGOTTEN. When the first version of
this application was submitted, no-one from Planning (or the developer)
informed or sent a "Neighbour Notification" letter to the Distillery
which derives all of its water for making whiskey from that stream, which
runs alongside the development!. The Distillery is only about 200 yards
from the boundary of the site.
 |
31. MOVED WITHOUT NOTICE. The Developer
changed his last published plan and submitted an amended version which
included
moving
a proposed new two-storey semi-detached dwelling some 4.5m (almost 15
feet) nearer to the boundary of an existing bungalow directly abutting
the site. This existing bungalow never appeared on any plan. The Coleraine
Planning Service approved this plan. The new building will now be one
third nearer. Yet neither the Developer nor the Planners informed
the bungalow owner of this change and the very existence of this new
layout
was never publicly advertised in the local Press.
On 11th September 2004 we wrote to the Divisional Planning Manager asking
if '....the above scenario
is normal and acceptable practice by the Planning Department?'
When she did not
answer we wrote to the Chief Executive asking the same question. Three
months after the initial query we received the following
reply which was endorsed by the Planning Secretariat.
This is a paraphrase of the lady's reply. The full correspondence can
be seen in the Public Application Files at the Coleraine Planning Sub-Division
"Not all amended plans
are re-advertised. In this case the plans addressed issues of
detail required to ensure
a quality
residential development…. All files are open to the public
therefore nothing is secret".
DIVISIONAL PLANNING MANAGER 13 Dec.2004
|
I have replied as follows:
"Detail? Seventeen
dwellings moved; two house types changed; a road moved 11m into
and along important wetland;
and two dwellings
omitted … and you call all these changes mere detail?
All these amendments are accepted by Planning and yet you put the
onus on the “objectors” to
find out by constantly booking to see the Application Files then visiting them
just in case amendments are made which planners aren’t publicising. This
is totally irresponsible. But then that’s how you also treated the Environmental
Heritage Agency" [See item 21 above] |

|
UPDATED 20TH NOV 2005
32. TREES ON WAYLEAVE. The Decision Notice
for 0248 states "All planting incorporated in the stamped approved
landscape plan shall be carried out in full in the first
available planting season...."
But this landscape plan shows a row of trees to be planted over sewer pipes.
These can be found in the North East corner of Site 0248, near the Straid Road.
The trees are to be Alnus Glutinosa, (Common Alder) which according to my Tree
books can grow up to 70 feet tall.!
On 11th September 2004 we wrote to the Divisional Planning Manager asking '......
why have you included in the Decision Notice .... a condition that
advocates planting a row of trees directly above a sewer line and well
within the 6m wayleave?'
When she did not
answer we wrote to the Chief Executive asking the same question. Three
months after the initial query we received the following
reply which was endorsed by the Planning Secretariat.
This is a paraphrase of the lady's reply. The full correspondence can
be seen in the Public Application Files at the Coleraine Planning Sub-Division
“Landscaping will obviously take
account of the position of services on the site”
DIVISIONAL PLANNING MANAGER 13 Dec.2004 |
I have replied as follows:
"Why use the words “in full” if
you don’t
mean them? Trees are extremely important to this sloping site,
especially to attempt to mask the rear gardens from the important
Straid Road (Main inland tourist route between Bushmills/Ballycastle).
Presumably that’s why the Landscape Architect put them
there.
In this sensitive sloping site I would have
thought Planners would have considered Landscaping, Layout and Services
as a whole, with trees not left to chance after the Services have
been put in. " (See photo further down this page in section
36) Also CLICK
to see line of sewer - this will open in a separate window which
will need closing |

|
33. NO ILLUSTRATIONS . Many of the planning guidelines
ask for illustrations to give planners an idea of what is being
proposed. i.e..-
|
- "Inclusion of relevant perspective views can also be of
value". [PPS1 Annex iii]
|
- "Diagrammatic illustration outlining the potential" [Creating
Places 3.3]
|
- "Photomontages to give an accurate impression of what is
being proposed".[Creating Places” App.B.1]
|
But as far as we can ascertain, by trawling through the Application
Files, no illustrations were ever supplied or even asked for by
Planners.
On 11th September 2004 we wrote to the Divisional Planning Manager
asking ' .....When none
was forthcoming, why did the Planners not request illustrative
material as recommended in the various guidelines?'
When she did not
answer we wrote to the Chief Executive asking the same question. Three
months after the initial query we received the following
reply which was endorsed by the Planning Secretariat.
This is a paraphrase of the lady's reply. The full correspondence can
be seen in the Public Application Files at the Coleraine Planning Sub-Division
| The Divisional Planning Manager did not answer this question.
But instead said "As this was a full
application and details of layout, landscaping and house types
were submitted, we were in a position
to assess whether the proposal would result in a quality residential
environment". |
I have replied as follows:
| "That response, I guess, sums up your
Departments’ appreciation
of the various Guidelines extolling the usefulness of illustrative
material (One calls it a “critical element” in
the process)" |
|
|
34.NO CONTEXT STATEMENTS. Many of
the planning guidelines ask for context statements to give planners
an idea
of what is being proposed. i.e..-
|
- “ Applicants for planning permission will be required,
as a minimum, [to] provide a short written statement setting out
the design principles adopted..” [PPS1 Annex iii published
way back in 1998]
|
- "Should be supported by sketch plans and a written statement
setting out the overall design concept" [Creating Places 3.03]
|
- "Recommend this be subject to a full site /context analysis
and concept statement."
[Case Officer for this development writing in July 2001]
|
We have trawled through the Open Application Files on several
occasions but never found any context statements.
|
On 11th September 2004 we wrote to the Divisional
Planning Manager requesting :-
'....Please could you tell me why your department did not insist on
the developer supplying a context statement?'
When she did not
answer we wrote to the Chief Executive asking the same question. Three
months after the initial query we received the following
reply which was endorsed by the Planning Secretariat.
This is a paraphrase of the lady's reply. The full correspondence can
be seen in the Public Application Files at the Coleraine Planning Sub-Division
“Concept” plans were received.
As layout, landscaping and house types were submitted, little
emphasis was placed on
the submission of a concept statement.
DIVISIONAL PLANNING
MANAGER 13 Dec.2004 |
I have replied as follows:
"CONTEXT: There appears
to be some confusion over “Context” and “Concept” In
this particular case with the proposed two storey dwellings
being
placed very near existing bungalows; the site’s position
near a main tourist route; in full view of the much visited
Distillery; and bounded by the precious St. Columns Rill (Distillery
Burn). Context is/was very important. Indeed one of your own
Senior Professional and Technical Officers wrote to the Case
Officer, in a consultation response, 23rd July 2001 “… “Should
be subject to a full site/context analysis…” and
he underlined those words. You would appear to ignore the advice
of one of your own senior Planning Officers.
CONCEPT PLANS: I note a Concept Plan was received 11th Dec 2001". |

|
|
|
|
35 PROCRASTINATION. It took seven months
from the time the Planning Authority recommended, and Moyle Council agreed,
for
this development to go ahead, before the Decision Notices were issued.
Why the delay? According to the list of various agencies, all were in
agreement with it proceeding. (Although see the confusion re EHS
elsewhere on this site). Incidentally the decision notices were
finally signed and issued by the Divisional Planning Manager the day
before he retired.
On 11th September 2004 we wrote to the Divisional Planning Manager,
pointing out that as far as we could see in the files they had received
only two letters during those seven months and asking
why the delay before issuing the decision notices?
When she did not
answer we wrote to the Chief Executive asking the same question. Three
months after the initial query we received the following
reply which was endorsed by the Planning Secretariat.
This is a paraphrase of the lady's reply. The full correspondence can
be seen in the Public Application Files at the Coleraine Planning Sub-Division
“As you point out in your letter a considerable amount of
correspondence was received … which contributed to the delay…”
DIVISIONAL PLANNING MANAGER
13 Dec.2004 |
I have replied as follows:
| "This is incorrect. I pointed
out in my letter there were two letters
received during that period: one from ourselves and one from EHS.
However I now amend that to three from ourselves.
So, as far as I am aware there were only four letters in total.
And you call four letters in seven months a “considerable
amount”?
Or were there other letters which did not appear where the
public can see them?
The contents of all four letters
necessitated, and received, only simple replies.
My letter one: - What plans/cross sections were being used by Rivers
Agency & EHS?
Why no temporary site entrance on the plan? What are the SUDS arrangements?
My letter two: - What is drawing number of the approved plan? (Received a one-sentence
reply)
My letter three: - Queried the many differences between the last published plan
and the approved plan (Received a one-sentence reply)
EHS Letter: - Stated they were not happy with the
approved plan. (Got a four line handwritten reply)" |

|
NEW
36. REAR ELEVATIONS FACE TOURISTS. Writing about the
original plan in August 2001 a Senior Professional and Technical Officer
(SPTO), who was a member of the Development Plan Team reported to the
Case Officer ..."I would not consider the present
proposal appropriate - view right across the rear gardens from the Straid
Road" There were 12 rear gardens facing the Straid Rd on that
original plan.
Three amendments later and the "approved" plan now has 16 rear
gardens- i.e. even more!- facing the Straid Rd.

With construction underway, here's a photo taken from the Straid Rd on
19th Nov 05 showing 14 of those rear gardens. NB The Straid Rd is the
main tourist inland country route between Bushmills and Ballycastle. This
has been described in a letter to us (13-12-04) from
the Divisional Planning Manager as a "Quality residential development"
|
If you can shed light on, or add to, any of the above points, then
please write or contact us at 32 Eagry Park, or by phone, or by email
on : - brian@eagry.com
Thanks |
Top |
| << Return to first page of Eagry |