THE DEVELOPMENT OFF EAGRY now known as EAGRY GARDENS

A SUMMARY AND OBSERVATIONS
Not in any particular order but numbered for ease of identification.
All links will open in a separate window which will need closing

Do feel free to read all of the following, but because there are so many paragraphs I have also made this list with links, for you to cherry pick what takes your fancy:

1 EXISTING PROPERTIES OMITTED.
2 BUILDING ON FLOODPLAIN.  
3 NON-ADVERTISED PLAN ACCEPTED.  
4 NON ADVERTISED PUBLIC ENQUIRY  
5 CONSTRUCTION TRAFFIC.  
6 OVERDEVELOPMENT.  
7 HOUSE MIX  
8 STANDARD HOUSES.  
9 TWO AND HALF HOUR TRAFFIC SURVEY  
10 WHAT'S TO BE BUILT?  
11 DEVELOPING ON WETLAND.  
12 COUNCIL ACCEPTANCE  
13 GLOBAL WARMING.  
14 COUNCIL AGENDA.  
15 CONSPICUOUS DWELLINGS.  
16 IS THIS DEVELOPMENT NECESSARY?  
17 NEIGHBOUR NOTIFICATION IS NOT A LEGAL EQUIREMENT  
18. BUILDERS CAN START WORK BEFORE PLANNING PERMISION  
19 TOO FEW ENFORCEMENT OFFICERS  
20 BUILDERS CAN BUILD ON FLOODPLAIN.  
21. MEMBERS OF PUBLIC ALERT EHS NATURAL HERITAGE TO PLANS.  
22 COUNTLESS GUIDELINES IGNORED  
23 PLANNING PROCESS IN DISARRAY  
25 HEDGES TORN OUT IN CLOSED SEASON.  
26 .EHS (NATURAL HERITAGE) 'SERIOUS CONCERNS' CONSIDERED "UNREASONABLE"  
26a. A LAW NEEDED TO FORCE A REPLY FROM ONE DEPT TO ANOTHER?  
26b. NO ACTION ON DECISION NOTICE ERRORS.  
27 WRONG HOUSE TYPE BUILT  
28 MISSING BEDROOM. (Contradictory Plans)  
29. STORM PIPELINE. (Contradictory plans)  
30 DISTILLERY FORGOTTEN. (Neighbour notification)  
31 MOVED WITHOUT NOTICE.  
32 TREES ON WAYLEAVE. (Contradictory plans)  
33. NO ILLUSTRATIONS ASKED FOR OR GIVEN  
34 NO CONTEXT STATEMENTS and WHO DECIDES WHICH GUIDELINES TO IGNORE?  
35 PROCRASTINATION. (Seven months between Approval and Decision Notices)  
36 REAR ELEVATIONS/GARDENS FACE TOURISTS.  
<< Return to home page of this Eagry web site


1. EXISTING PROPERTIES OMITTED. Not a single plan submitted to the Planners carried the location of the twenty Eagry houses which border the site. (With the exception of two houses). So even now, fourten months after the plans were approved, we are not sure what is to be built behind us and what it's position is. Surely we have a right to know this information. At least two of the Planners' own guidelines booklets state that locations of existing abutting dwellings should be shown.Yet the planners never asked for this and what's more we were told by the then Divisional Planning Manager that it was unnecessary

We say the law needs changing to insist developers use up-to-date location maps and which also show adjacent properties. (See Plans page)

On 11th September 2004 we wrote to the Divisional Planning Manager asking .... 'why your department did not insist that all the existing Eagry properties which bound the southern edge of the site, be shown on the plans?'
When she did not answer we wrote to the Chief Executive asking the same question. Three months after the initial query we received the following reply which was endorsed by the Planning Secretariat. This is a paraphrase of the lady's reply. The full correspondence can be seen in the Public Application Files at the Coleraine Planning Sub-Division

"There is no requirement to show position of dwellings on adjacent lands".
DIVISIONAL PLANNING MANAGER 13 Dec.2004
I have replied as follows:
"From your reply it would appear planners need a “requirement” to hide behind, rather than taking pity on and informing neighbours of the position of their property in relation to this new development of 2 storey dwellings which will overshadow and loom over their existing bungalows?"


2. BUILDING ON FLOODPLAIN. 18 th November 2003, Rivers Agency advised Planning Service "against permitting development in floodplains or the in-filling of floodplains to facilitate development". (They even included a large scale map defining the area) Yet that same department, in the same letter, in the same paragraph, accepted infilling encroaching, in places by more than 75%, into the very 100 year flood area which they defined. (See Flooding Pages)

And way back in August 2001, referring to the original plan, Rivers Agency wrote to the Planners
"Rivers Agency is opposed to any infilling for development purposes, in areas of flood pondage, as the resultant displacement of flood water can cause problems elsewhere within the catchment."

On 11th September 2004 we wrote to the Divisional Planning Manager asking' ....Why was the nonsensical paragraph from Rivers Agency included in the Decision Notices Informatives and not queried with them and resolved before getting to this stage? And what advice will you be giving to the Enforcement Officer once construction work starts within the above ‘no-build’ zone? ‘Ignore the Decision Notice’? In which case why have a Decision Notice?'
When she did not answer we wrote to the Chief Executive asking the same question. Three months after the initial query we received the following reply which was endorsed by the Planning Secretariat. This is a paraphrase of the lady's reply. The full correspondence can be seen in the Public Application Files at the Coleraine Planning Sub-Division

"A/. This was an informative and “people buying a dwelling and their solicitors will wish to satisfy themselves that the prescribed levels have been adhered to”.
B/. “Rivers Agency addressed the issues relating to flood-plain in their letter to you 9th March 2004”

Enforcement will not be required … Enforcement action cannot be taken on Informatives."
DIVISIONAL PLANNING MANAGER 13 Dec.2004
I have replied as follows:

"You did not answer the question “Why did you not query…..?”
Well at least I queried this contradictory Rivers Agency statement. Which is more than Planners apparently did.
A/. Writing (21-5-02) about an earlier version of this plan, a member of the Rivers Agency, said “Rivers Agency has made the Planning Authority aware that flooding can occur adjacent to the Distillery Burn… It is a matter for the Planning Authority to approve any development at this location”.
Now here you [Divisional Planning Manager] are, saying it is up to the Solicitor and prospective purchaser to satisfy themselves the prescribed levels have been adhered to. Is no-one willing to accept responsibility anymore?

B/. Twice I wrote to the Rivers Agency - 16 Feb 2004 to the Chief Executive and again 22 March 2004 to the Director of Operations.
I wrote to the Dir of Ops. as I was not satisfied with the Chief Exec.'s earlier answer - the answer that you quoted as sent to me on 9th March 04 and which you say “addressed “ the issue. ‘Addressed’ but certainly not answered to my satisfaction. If Planners meekly accept such ambiguity I will not.
By insisting on clarification from the Rivers Agency, the planners could have averted the disappointment when prospective purchasers of four of these dwellings discover their new homes are partly in a known floodplain. " (NEW - See photo album of flooding which occured on 12 March 2006. Opens in separate window)

"It hasn’t gone away you know.
Above photo taken 8th Jan 05. Site 0247 in foreground. I note Angela Smith (Minister for the Environment) is asking for comment on the “Consultation Draft PPS 15 – Planning and Flood Risk”. I will, of course, be sending her all the relevant correspondence associated with this particular flood plain fiasco.

["Enforcement action cannot be taken on informatives"] At least this absolves enforcement officers when the road/dwellings are flooded or subsidence takes place and the inevitable enquiry ensues."


3. NON-ADVERTISED PLAN ACCEPTED. Several agencies referred to the drawing dated 28th May 2003 (Drg 02/55:22) as the "final layout". We were confused as this was not the last plan advertised in the local Press which was the July 2002 version. So we queried this (18th March 2004) with the Divisional Planning Manager asking what Layout Plan/Drawing number was finally approved by Planning Service and taken to Moyle Council in November 2003? . We have subsequently received a reply (7/4/04) stating the approved plan was drawing no. 02/55:02 (30th May 2003). But this layout has never appeared in the local press Planning Applications.
Compared to the previous plan, - of the 26 dwellings which directly abut onto the established Eagry dwellings, 21 of them have been changed (Four moved further away and 17 moved nearer- up to one third nearer in some cases) There are many other changes too, so see Differ page to compare the differences.

We sent a comprehensive list of these differences, together with a drawing showing the two plans superimposed, to the Divisional Planning Manager on 18th April 2004. But after a month had passed without even an acknowledgement we sent another copy of the same documents to the Manager again, on 18th May 2004 (only this time to be “signed for on delivery”). We then had a speedy reply apologising for not acknowledging our first letter. And noting that the points raised “will be fully considered before any decision is issued on these applications” That’s an ambiguous statement and does not necessarily mean they are even considering our request for the plan to be advertised.

On 29th June 2004 the "Decision Notices" were issued giving the go-ahead to this unpublished plan. What's the word used to describe an event when two parties proceed with a plan without telling the third party who is also involved? - Duplicity? Collusion?

On 11th September 2004 we wrote to the Divisional Planning Manager asking ..... 'why the Amended Plan (Drawing No. 02 received 30/5/03) was not advertised in the local press?'
When she did not answer we wrote to the Chief Executive asking the same question. Three months after the initial query we received the following reply which was endorsed by the Planning Secretariat. This is a paraphrase of the lady's reply. The full correspondence can be seen in the Public Application Files at the Coleraine Planning Sub-Division

"In this case the plans addressed issues of detail required to ensure a quality residential development…. All files are open to the public therefore nothing is secret"
DIVISIONAL PLANNING MANAGER 13 Dec.2004 
I have replied as follows:

"Detail? Seventeen dwellings moved; two house types changed; a road moved 11m into and along important wetland; and two dwellings omitted … and you call all these changes mere detail?
All these amendments are accepted by Planning and yet you put the onus on the “objectors” to find out by constantly visiting the files in Coleraine just in case amendments are made which planners aren’t publicising. This is totally irresponsible. But then that’s how you also treated the Environmental Heritage Agency (See 21).

What timescale and how often do you recommend objectors should monitor the Files?"

RESPONSE FROM PLANNERS 18th March 05
"It is for the objector(s) to make a judgement as to the frequency with which they should or would wish to view application files"!

4. NON ADVERTISED PUBLIC ENQUIRY. A Public Enquiry was held to discuss proposed new housing developments in the Bushmills area. Although deeply affected by one such proposal, Eagry residents were not informed of this event, even though objectors to another development were sent individual invitations. Although billed as a "public" enquiry we are unaware of any advertising in the local press. (See Public Enquiry page)

5. CONSTRUCTION TRAFFIC. Residents are concerned that the heavy construction traffic will use the narrow, steep Eagry Park road to get to the new site. Road's Service answer to their worries was summed up in one sentence..." common sense would tell one that if a housing development is to be extended there will be construction traffic using the existing road“ (See Site Traffic page) The developers have now been given approval for a temporary site entrance directly off the Straid Road. But this is only for two years so the top site traffic (0247) might still use Eagry.

6. OVERDEVELOPMENT. The first amended plan was refused as it was "...contrary to Planning Policy Statement 7 : Quality Residential Environments' - Overdevelopment". Yet that plan did not even show the house types. (See Visual Impact page) They could have been one-bedroomed huts or six storeys high flats for all the Planners knew.

7.HOUSE MIX. The original, refused, proposal showed a mixture of two storey houses and bungalows on the skyline at different angles to each other and painted white. But the approved plan shows a 'wall' consisting of a straight row of terraces and two-storey houses, one of the terraces having dark grey exterior walls. Is that visually more attractive? (See Visual Impact page)


8. STANDARD HOUSES. In a note which accompanied the original plan, a member of the Planning Development team wrote ..."There is a continued use of standard house-types, which have featured widely in other locations".
There were twenty six of house type MD41 in the original proposed plan.
Planning Service has now approved the latest layout, which includes twenty four type MD41. Just two less. And I have not even included the mid-terraced houses which have several more of these MD41 types lumped together. (See Visual Impact page) And the developer has even attempted to add another set of MD41's But building of this pair has appears to have ceased after Enforcement issued a warning letter. CLICK to see this wrong building

On 11th September 2004 we wrote to the Divisional Planning Manager asking ' ...... Why were these plans accepted which show a continued use of existing house types?'
When she did not answer we wrote to the Chief Executive asking the same question. Three months after the initial query we received the following reply which was endorsed by the Planning Secretariat. This is a paraphrase of the lady's reply. The full correspondence can be seen in the Public Application Files at the Coleraine Planning Sub-Division

"It is not unusual to re-use the same house types. The comment made by the original Case Officer was not a complaint more an observation."
DIVISIONAL PLANNING MANAGER 13 Dec.2004 
I have replied as follows:

"CREATING PLACES 3.32 states: “An even distribution throughout the layout of developers’ standard ranges of dwelling designs should be avoided”.
But you, Divisional Planning Manager, don’t acknowledge this statement. (I expect you call this an “Observation”) In fact go as far as to accept it as being ‘not unusual’.

But this was a Policy statement.
In my original letter to you I was not quoting the Case Officer – saying ‘there is a continued use of standard house types used elsewhere’ - but a Senior Professional and Technical Officer who was a member of your Development Team writing to the Case officer on 23-7-01. and quoted by that Case Officer after her site visit on 27-07-01, under her section “Assessment of Policy”. But no matter who said it, I cannot see them bothering to make this “observation” without inferring that this comment has a bearing on the proposed development and that using the same house types is bad design. Hence it coming under the Case Officer’s heading of “Assessment of policy”

9. TWO AND HALF HOUR TRAFFIC SURVEY. The first amended plan was turned down because, amongst other reasons, there was "unsatisfactory access" . However as a result of a one day traffic survey spread over two and a half hours this was changed to being "acceptable". Surely such a paltry survey is not worth the paper it's written on? The survey took place during commuting hours yet much of the present Eagry traffic, and no-doubt the extra new development traffic as well, will consist of holiday makers who are not commuting. (See Residential Traffic page)

10. WHAT'S TO BE BUILT? The plan was approved last November 2003. Construction work started on the site on 16th Jan 2004. The Decision Notices were issued on 29th June 2003 yet the approved plan was never published, so all we can do is look out of our back windows and watch the construction work progress and wonder what is to be built behind us? (See Work Started page)


11. DEVELOPING ON WETLAND. Part of the land scheduled for this development is wetland. "One of the few wetland areas in North Antrim". In 1971, Governments around the world signed up to to preserve wetlands. Yet here is development and in-filling on our very own rare wetland being allowed by Coleraine Planning to take place. We say - "lip service", that's all these conventions are when flouted in this manner. (See Trees and plants section).

"Economic difficulties of the Province have meant that there has tended to be a bias in favour of the landowner and developer, sometimes at the expense of the environment" Parliamentary Environment Committee report (Rossi) 1990 (Not much change there in 15 years!)

12. COUNCIL ACCEPTANCE How do the Moyle Councillors view a new estate of 66 houses? - What is their most important criteria when accepting a new development? -----

12a. The look of the estate in this Area of Natural Beauty?
12b. As affordable housing for young members of the Bushmills community? New terraced houses built by the same developer are on sale in Bushmills for £110,000 and, according to their adverts, would be "....Ideal holiday or investment homes"
12c. As more second homes?
12d. As more dwellings (no matter what standard and no matter for whom they are aimed) which mean more rates to be paid by the new owners? (See Council page)

13. GLOBAL WARMING. In spite of all the talk of global warming, flooding etc, here, in the year 2005, is a development still being allowed to go-ahead and build on a flood plain (See Flooding page)

14.COUNCIL AGENDA. On 24th November 2003, Moyle Council debated (well actually there was no debate) and approved this planning application. We (the objectors) were not told this item was on the agenda so did not attend to hear our Councillors represent us. Surely this meeting and what was to be discussed should have been advertised? We say methods (not just the internet) need to be put in place to enable people to know what is coming up at the next Moyle Council meeting.(See Council page).

The Planning Service now posts a list of Planning Applications coming up before Councils. CLICK HERE to see it

15. CONSPICUOUS DWELLINGS. In the original proposal there were 2 x detached two-storey houses and 3 x bungalows on the highest part of the site. Now the latest -and accepted- plan shows those dwellings replaced by a two-storey terrace of four dwellings and 2 x two-storey semi-detached houses. (The bungalows have gone). Are we to presume that Planners are happier to accept a two storey terrace instead of bungalows at the highest and visually most noticeable part of the development? (See Visual Impact page)

16. NECESSARY.Is this Development necessary? Who wants sixty six new dwellings of this size and price in Bushmills? Please reply to the contact given below. According to one objector, at one time it is believed there was "over 1,200 dwellings (apartments etc) which cannot find owners in the North East" (See Needed page)

17. NOTIFICATION It is NOT a statuary requirement of Planners to issue Neighbour Notifications. We say this should be made law (See Work Started page)

18. START WORK It is not illegal for a developer to go on site and start work before Planning Permission is granted. We say starting work on a site before obtaining written permission should be made against the law.(See Work Started page)

19.ENFORCEMENT We understand there are 22 enforcement officers for the whole of Northern Ireland. We say these need to be augmented. (See Enforcement page)

20. BUILD ON FLOODPLAIN. Builders can go ahead and build on a flood plain and there is no way or law to stop them. Agencies can only advise and recommend they do not build. We say the law needs to be changed. (See Flooding page)


21. PUBLIC ALERTS EHS. Six months after a plan is approved, one agency expresses serious concerns about it!
On 6 November 2002 the Environment & Heritage Service, (Natural Heritage) agency accepted the proposed development. And it would appear, on the basis of their acceptance (and the other agencies as well), the plan was approved by the Planners in November 2003. But the plan EHS was accepting had been superseded. We think they were unaware of this new version, so wrote to the Divisional Planning Officer asking that EHS Natural Heritage be given sight of the new (approved) plan. He replied .... "In view of your queries, we will clarify any outstanding issues with EHS." This EHS Agency has now replied, thanking planning for the new documents, and saying they have "serious concerns with this amended proposal" and requesting several amendments. ( See Trees page) It would appear it took our enquiry to kick start the Planning Department to alert EHS to this amended plan. Draw your own conclusions re the efficiency of the system.

On 11th September 2004 we wrote to the Divisional Planning Manager asking why ... 'it took ourselves, who are members of the public, to alert yourselves and EHS to this important discrepancy?'
When she did not answer we wrote to the Chief Executive asking the same question. Three months after the initial query we received the following reply which was endorsed by the Planning Secretariat. This is a paraphrase of the lady's reply. The full correspondence can be seen in the Public Application Files at the Coleraine Planning Sub-Division

The Divisional Planning Manager did not reply to this question
I have replied as follows:
"Considering an amended plan without alerting one of the Agencies directly involved is a fundamental flaw in your system. Instead of ignoring my question (And your avoidance has been endorsed by the Planning Secretariat), I suggest this misadministration should be investigated to ensure this doesn't happen again."


22 COUNTLESS GUIDELINES IGNORED. Over the years the Planning Department has published many guidelines and policy recommendations. However the Coleraine Planning Department (and the developers) would appear to have deliberately ignored many of these guidelines in this proposed development. See Guidelines to read several pages of ignored recommendations. Here's just one :- Several Planning Guideline documents say that "Applicants will be required, as a minimum, (to) provide a short written statement setting out the design principles". However, no written statement was ever supplied nor, more interestingly, ever asked for, by the Planners.

And here's another:- "Developers will need to demonstrate that their proposals will avoid significant ... overlooking and loss of privacy. CLICK TO SEE PHOTO OF THE VERY FIRST BUILDING CONSTRUCTED!

We asked the Divisional Planning Manager   Who decides which guidelines are to be adhered to and which ones to ignore? 

"The final opinion is formulated by the Development Control Group."
DIVISIONAL PLANNING MANAGER 13 Dec.2004 
I have replied as follows:

"So it’s not the fault of one person but a collective decision to ignore guidelines?"

RESPONSE FROM PLANNERS 18th March 05 "The Development Control Group consists of an Authorised Officer and at least two other planning officers"

23..DISARRAY The Planning Process is in disarray. On this web site you will find examples of :-
Inefficiency. (EHS working to out-of-date plans)

Double speak (Rivers)

Terminological inexactitudes (That ignored "buffer" strip of land)

Layouts misread (Heritage)

Plans misread (a four bedroomed house with only three bedrooms)

Dubious surveys (Roads)

Procrastination (5 weeks to even acknowledge a letter, three months to answer it-Planning)

Procrastination (Plan Approved Nov 2003. Decision Notices finally issued June 2004)

Overwhelmed staff (Planning)

Platitudes (Rivers SUDS)

Ignored environment (Building over wet lands)

Secrecy (Unpublished layout approved)

Deviousness (Existing properties omitted from plans)

Lessons ignored (Building over floodplain)

Policy guidelines totally ignored,

Plans stamped "approved" but not even read (only 3 beds in 4 bedroomed plan)

and a Council which apparently unanimously welcomes second homes.
24.
25. HEDGES. Under the Wildlife (NI) Order 1985, it is an offence to damage or destroy the nest of any wild bird whilst it is being used or built, or disturb any wild bird while on or near a nest that is being built. And under Good Farming Practice the trimming of hedges is not permitted from 1st March until 31st August. But there appears to be somme confusion about weather the law applies to construction workers. (in the case of this development hedges have been ripped out during the nesting season) . This Wildlife Order needs to be clarified.


26.EHS 'SERIOUS CONCERNS' CONSIDERED "UNREASONABLE" In a letter (1st April 2004) to the Planning Service, EHS Natural Heritage had .."serious concerns with this amended proposal Here is an extract from that letter:

"..we requested a 10m no development zone along the stream, which was to have a planting belt of native species. We are concerned that the drawings indicate proposed infill within the 10m corridor and that fencing is proposed along the river edge. We request amendments to the proposals to ensure that no infill, development, fencing, ground disturbance or re-seeding takes place within the 10m zone." [MY EMPHASIS]

Apart from omitting the fence, these requests have been totally ignored and the planners have allowed infilling, development, ground disturbance and reseeding, all to take place within the 10m zone. There's a 80m (262 feet ) long road embankment to be built which will run lengthwise within this zone. But this was meant to be a tree belt and wildlife corridor.

On 11th September 2004 we wrote to the Divisional Planning Manager asking' ....why these concerns by EHS Natural Heritage were not addressed?'
When she did not answer we wrote to the Chief Executive asking the same question. Three months after the initial query we received the following reply which was endorsed by the Planning Secretariat. This is a paraphrase of the lady's reply. The full correspondence can be seen in the Public Application Files at the Coleraine Planning Sub-Division

"The amendments were accepted in their [EHS] letter July 2002 (Copy enclosed) … but EHS concerns in April 2004 that their requested 10m zone should still apply were considered unreasonable". DIVISIONAL PLANNING MANAGER 13 Dec.2004
I have replied as follows:
"You refer to EHS accepting an amended plan in July 2002. I agree, they did, but that is the whole point of my complaint. The plan (Drg. 04) to which they agreed was superseded in many respects after that, and in the final accepted plan an embankment is to be built through, along and within that zone. Yet you still held their year-out-of-date acceptance as valid.

Your reply to me says a copy of EHS July 2002 letter is enclosed. But it was not. I suspect because it contains the embarrassing (to you) sentence…”The planting belt should be a minimum width of 10m of locally native specimens of Alder and Willow"

To sum up;
On 19th February 2002, a year before the final amended plan was accepted, EHS wrote the following to your department “…no development should take place within 10m of the river and the site layout should be redesigned accordingly.”

On 8th July 2002 EHS wrote, …”The planting belt should be a minimum width of 10m of locally native specimens of Alder and Willow”

On 28th October 2002 EHS wrote, “ …A wildlife corridor must be provided through the site. The 10m strip of trees along the stream can accommodate this,”

On 1st April 2004 EHS wrote …”We request amendments to the proposals to ensure that no infill, development, fencing, ground disturbance or re-seeding takes place within the 10m zone."

Yet after all the above pleadings over the years, that request is deemed by the then Divisional Planning Manager as “unreasonable”.
On 6th April 2004 his handwritten note reads as follows ….

I have reprinted it here because, even allowing for the degredation by the web reproduction process, it is very hard to decipher. Which is a pity, considering what an important statement this is. I have put a question mark against words I am uncertain about.
"I am satisfied that following the lengthy negotiations and agreements with the agents it would be unreasonable to seek further amendments(?) to the scheme which is in all other respects, entirely(?) satisfactory. However a condition omitting the fence should be attached to the approval". (A Planning Officer confirmed the signature to be that of the then Divisional Planning Manager)"


26a. A LAW TO FORCE A REPLY? At the time of writing this paragraph (30/10/04), a public consultation paper (Click for pdf copy) has been published in which people are being asked to comment on “Proposals to Amend Primary Planning Legislation in Northern Ireland”.
One of the questions posed is: - “Do you consider that … there are any benefits in a legislative requirement for consultees to respond to consultation requests within a specified timescale?”
What a reflection on the Civil Servants who run the various agencies - Water; Rivers; Environmental Heritage etc. that Government is even considering a law to force them to reply to Planners’ queries in a “specified time”?
Imagine if this happened in the private sector, say British Airways, and it took a law to force one department to reply in a specified time to a request from another?

Not that it matters, because when an agency does reply the Planners ignore them (See Par 26 above)


26b. NO ACTION ON DECISION NOTICE ERRORS. The final Decision Notices have several anomalies. Paragraph 10 for instance refers to the Landscape Plan drawing No 14 dated 13 February 2003. Whereas in actual fact this particular drawing is of a house type and nothing to do with a landscape plan. CLICK for more mistakes in the Decision Notices

On 11th September 2004 we wrote to the Divisional Planning Manager asking '... Are Decision Notices legal documents? And if so, and errors are discovered, does the Notice have to be withdrawn and a new one drawn up and issued?'
When she did not answer we wrote to the Chief Executive asking the same question. Three months after the initial query we received the following reply which was endorsed by the Planning Secretariat. This is a paraphrase of the lady's reply. The full correspondence can be seen in the Public Application Files at the Coleraine Planning Sub-Division

The Divisional Planning Manager did not answer this question about them being legal documents. Although in answer to another question she did say ; "It's a matter for the Courts to interpret a planning decision where ambiguity occurs"

She went on to say “I accept there has been a number of typographical errors…I am satisfied that the various conditions can still be enforced”.
DIVISIONAL PLANNING MANAGER 13 Dec.2004
I have replied as follows:

"I cannot think of any reason why you did not answer this simple question [Are Decision Notices legal documents?] except, perhaps, that you don’t know the answer. However you’ll be interested to know a lady representing the Planning Secretariat wrote to say she had nothing further to add to your replies, so I can only assume the Secretariat doesn’t know the answer either.

I note you make no mention of amending the Decision Notices. Yet in the “Reforming Planning. Public Consultation Paper August 2004” the… “Department proposes to introduce a legislative framework whereby simple omissions or minor errors contained in Departmental planning decision notices can be amended after decisions have been issued”
Why are they bothering to consider this when Coleraine Planning Sub-Division appears to be content to let errors stand?"

27. WRONG HOUSE TYPE BUILT. The very first building has now reached the second floor of construction. AND IT IS NOT WHAT WAS APPROVED by the Planning Decision Notice. What should be built is a semi chalet type with no windows at the second storey but Velux windows in the roof. What in fact has been built is a semi with windows on the second storey which are looking straight down into the existing Eagry Park bungalows, back rooms and gardens. The building is also approximately three feet higher than approved. CLICK for details

Update October 30, 2004 The Enforcement section of the Sub-Divisional Planning Office (Coleraine) visited the site and on 26th August 2004 issued "...a warning letter advising the developer that a breach had occurred and that they are proceeding at their own risk. ....As no response has been received from the builder, the Department now intends to send a final warning letter seeking compliance with the approved plans." The top storey blocks have now been removed and work has started on the "accepted" lower version of this set of semis.



28. MISSING BEDROOM. Drawing 08 received 5th November 2003 has been stamped “Approved”. It is a plan and elevations of house type MD96 which, according to the main layout drawing 02, is a four bedroomed detached dwelling. But there are only three bedrooms drawn. - Bedrooms 2,3 and 4. - Curiously no bedroom number one appears. In fact there does not seem to be space to build a bedroom number one. It can’t be that the developer is planning to offer the lounge as an alternative bedroom because all the other house types with four bedrooms all have lounges as well (Types MD86A and MD86 for instance).

On 11th September 2004 we wrote to the Divisional Planning Manager asking '.....Does your department study plans and elevations of house types submitted to them? Presumably so, otherwise they would not require them to be sent in. And if they do, and find an irregularity, ie Type MD96, should they not query it with the developer and ask for new plans to be submitted?'
When she did not answer we wrote to the Chief Executive asking the same question. Three months after the initial query we received the following reply which was endorsed by the Planning Secretariat. This is a paraphrase of the lady's reply. The full correspondence can be seen in the Public Application Files at the Coleraine Planning Sub-Division

"Planning Service require the submission of house types for three purposes. To ensure a range of house types; check footprint v site curtilage; ensure elevation detail is acceptable….The type MD96 is a three bedroomed dwelling and not as you indicated".
DIVISIONAL PLANNING MANAGER 13 Dec.2004

I have replied as follows:

"Thanks for that information. Drawing 08 was obviously superseded with a different version, which I did not buy a copy of.
However if this is a three bedroomed dwelling why does the ‘Approved’ main layout drawing (02/55:02 received 30th May 2003) show, in it’s list of house types, that the five type MD96 dwellings are FOUR bedroomed? From this ambiguity it would appear that the planners know more about what the developer is to build than the developer himself?
If they build a four bedroomed dwelling but you say their plan shows only a three bedroomed one, then I assume they will need to apply for a change of house type and you will have to advertise same. "

RESPONSE FROM PLANNERS 18th March 05 [In answer to the above question 'Will they have to re-advertise?' ] "Yes" (they will have to re-advertise)


29. STORM PIPELINE. A note on Drawing 02 states “Each dwelling shall be provided with a… 150mm dia. storm pipeline to the public sewer” Yet the actual drawing shows a completely separate storm pipeline running throughout the development and not connected to the public sewer. This contradiction was not "picked up" by the Planners and the drawing has subsequently been stamped "approved"

On 11th September 2004 we wrote to the Divisional Planning Manager asking ' .... how has your Department interpreted these apparently opposite confusing instructions?'
When she did not answer we wrote to the Chief Executive asking the same question. Three months after the initial query we received the following reply which was endorsed by the Planning Secretariat. This is a paraphrase of the lady's reply. The full correspondence can be seen in the Public Application Files at the Coleraine Planning Sub-Division

The Divisional Planning Manager did not attempt to explain this anomaly, instead said the Developer has to liaise with the Water Service.
I have replied as follows
"So when drafting Decision Notices and Informatives why bother using phrases such as “Should be carried out in full” or “In accordance with stamped approved“, when final decisions are being made which must go against these set-in-stone drawings? I suggest you drop these phrases if you don’t mean them. "

30. DISTILLERY FORGOTTEN. When the first version of this application was submitted, no-one from Planning (or the developer) informed or sent a "Neighbour Notification" letter to the Distillery which derives all of its water for making whiskey from that stream, which runs alongside the development!. The Distillery is only about 200 yards from the boundary of the site.


31. MOVED WITHOUT NOTICE. The Developer changed his last published plan and submitted an amended version which included moving a proposed new two-storey semi-detached dwelling some 4.5m (almost 15 feet) nearer to the boundary of an existing bungalow directly abutting the site. This existing bungalow never appeared on any plan. The Coleraine Planning Service approved this plan. The new building will now be one third nearer. Yet neither the Developer nor the Planners informed the bungalow owner of this change and the very existence of this new layout was never publicly advertised in the local Press.

On 11th September 2004 we wrote to the Divisional Planning Manager asking if '....the above scenario is normal and acceptable practice by the Planning Department?' When she did not answer we wrote to the Chief Executive asking the same question. Three months after the initial query we received the following reply which was endorsed by the Planning Secretariat. This is a paraphrase of the lady's reply. The full correspondence can be seen in the Public Application Files at the Coleraine Planning Sub-Division

"Not all amended plans are re-advertised. In this case the plans addressed issues of detail required to ensure a quality residential development…. All files are open to the public therefore nothing is secret".
DIVISIONAL PLANNING MANAGER 13 Dec.2004

I have replied as follows:
"Detail? Seventeen dwellings moved; two house types changed; a road moved 11m into and along important wetland; and two dwellings omitted … and you call all these changes mere detail?
All these amendments are accepted by Planning and yet you put the onus on the “objectors” to find out by constantly booking to see the Application Files then visiting them just in case amendments are made which planners aren’t publicising. This is totally irresponsible. But then that’s how you also treated the Environmental Heritage Agency" [See item 21 above]

UPDATED 20TH NOV 2005
32. TREES ON WAYLEAVE. The Decision Notice for 0248 states "All planting incorporated in the stamped approved landscape plan shall be carried out in full in the first available planting season...."
But this landscape plan shows a row of trees to be planted over sewer pipes. These can be found in the North East corner of Site 0248, near the Straid Road. The trees are to be Alnus Glutinosa, (Common Alder) which according to my Tree books can grow up to 70 feet tall.!

On 11th September 2004 we wrote to the Divisional Planning Manager asking '...... why have you included in the Decision Notice .... a condition that advocates planting a row of trees directly above a sewer line and well within the 6m wayleave?' When she did not answer we wrote to the Chief Executive asking the same question. Three months after the initial query we received the following reply which was endorsed by the Planning Secretariat. This is a paraphrase of the lady's reply. The full correspondence can be seen in the Public Application Files at the Coleraine Planning Sub-Division

“Landscaping will obviously take account of the position of services on the site”
D
IVISIONAL PLANNING MANAGER 13 Dec.2004

I have replied as follows:

"Why use the words “in full” if you don’t mean them? Trees are extremely important to this sloping site, especially to attempt to mask the rear gardens from the important Straid Road (Main inland tourist route between Bushmills/Ballycastle). Presumably that’s why the Landscape Architect put them there.

In this sensitive sloping site I would have thought Planners would have considered Landscaping, Layout and Services as a whole, with trees not left to chance after the Services have been put in. " (See photo further down this page in section 36) Also CLICK to see line of sewer - this will open in a separate window which will need closing

33. NO ILLUSTRATIONS . Many of the planning guidelines ask for illustrations to give planners an idea of what is being proposed. i.e..-

  • "Inclusion of relevant perspective views can also be of value". [PPS1 Annex iii]
  • "Diagrammatic illustration outlining the potential" [Creating Places 3.3]
  • "Photomontages to give an accurate impression of what is being proposed".[Creating Places” App.B.1]

But as far as we can ascertain, by trawling through the Application Files, no illustrations were ever supplied or even asked for by Planners.

On 11th September 2004 we wrote to the Divisional Planning Manager asking ' .....When none was forthcoming, why did the Planners not request illustrative material as recommended in the various guidelines?' When she did not answer we wrote to the Chief Executive asking the same question. Three months after the initial query we received the following reply which was endorsed by the Planning Secretariat. This is a paraphrase of the lady's reply. The full correspondence can be seen in the Public Application Files at the Coleraine Planning Sub-Division

The Divisional Planning Manager did not answer this question. But instead said "As this was a full application and details of layout, landscaping and house types were submitted, we were in a position to assess whether the proposal would result in a quality residential environment".
I have replied as follows:
"That response, I guess, sums up your Departments’ appreciation of the various Guidelines extolling the usefulness of illustrative material (One calls it a “critical element” in the process)"


34.NO CONTEXT STATEMENTS. Many of the planning guidelines ask for context statements to give planners an idea of what is being proposed. i.e..-

  • “ Applicants for planning permission will be required, as a minimum, [to] provide a short written statement setting out the design principles adopted..” [PPS1 Annex iii published way back in 1998]
  • "Should be supported by sketch plans and a written statement setting out the overall design concept" [Creating Places 3.03]
  • "Recommend this be subject to a full site /context analysis and concept statement."
    [Case Officer for this development writing in July 2001]

We have trawled through the Open Application Files on several occasions but never found any context statements.

On 11th September 2004 we wrote to the Divisional Planning Manager requesting :-
'....Please could you tell me why your department did not insist on the developer supplying a context statement?'
When she did not answer we wrote to the Chief Executive asking the same question. Three months after the initial query we received the following reply which was endorsed by the Planning Secretariat. This is a paraphrase of the lady's reply. The full correspondence can be seen in the Public Application Files at the Coleraine Planning Sub-Division
“Concept” plans were received. As layout, landscaping and house types were submitted, little emphasis was placed on the submission of a concept statement.
D
IVISIONAL PLANNING MANAGER 13 Dec.2004   
I have replied as follows:
"CONTEXT: There appears to be some confusion over “Context” and “Concept” In this particular case with the proposed two storey dwellings being placed very near existing bungalows; the site’s position near a main tourist route; in full view of the much visited Distillery; and bounded by the precious St. Columns Rill (Distillery Burn). Context is/was very important. Indeed one of your own Senior Professional and Technical Officers wrote to the Case Officer, in a consultation response, 23rd July 2001 “… “Should be subject to a full site/context analysis…” and he underlined those words. You would appear to ignore the advice of one of your own senior Planning Officers.
CONCEPT PLANS: I note a Concept Plan was received 11th Dec 2001".


35 PROCRASTINATION. It took seven months from the time the Planning Authority recommended, and Moyle Council agreed, for this development to go ahead, before the Decision Notices were issued. Why the delay? According to the list of various agencies, all were in agreement with it proceeding. (Although see the confusion re EHS elsewhere on this site). Incidentally the decision notices were finally signed and issued by the Divisional Planning Manager the day before he retired.

On 11th September 2004 we wrote to the Divisional Planning Manager, pointing out that as far as we could see in the files they had received only two letters during those seven months and asking why the delay before issuing the decision notices? When she did not answer we wrote to the Chief Executive asking the same question. Three months after the initial query we received the following reply which was endorsed by the Planning Secretariat. This is a paraphrase of the lady's reply. The full correspondence can be seen in the Public Application Files at the Coleraine Planning Sub-Division

“As you point out in your letter a considerable amount of correspondence was received … which contributed to the delay…”
D
IVISIONAL PLANNING MANAGER 13 Dec.2004     
I have replied as follows:
"This is incorrect. I pointed out in my letter there were two letters received during that period: one from ourselves and one from EHS. However I now amend that to three from ourselves. So, as far as I am aware there were only four letters in total. And you call four letters in seven months a “considerable amount”?

Or were there other letters which did not appear where the public can see them?

The contents of all four letters necessitated, and received, only simple replies.
My letter one: - What plans/cross sections were being used by Rivers Agency & EHS? Why no temporary site entrance on the plan? What are the SUDS arrangements?
My letter two: - What is drawing number of the approved plan? (Received a one-sentence reply)
My letter three: - Queried the many differences between the last published plan and the approved plan (Received a one-sentence reply)

EHS Letter: - Stated they were not happy with the approved plan. (Got a four line handwritten reply)"

NEW
36. REAR ELEVATIONS FACE TOURISTS. Writing about the original plan in August 2001 a Senior Professional and Technical Officer (SPTO), who was a member of the Development Plan Team reported to the Case Officer ..."I would not consider the present proposal appropriate - view right across the rear gardens from the Straid Road" There were 12 rear gardens facing the Straid Rd on that original plan.
Three amendments later and the "approved" plan now has 16 rear gardens- i.e. even more!- facing the Straid Rd.

With construction underway, here's a photo taken from the Straid Rd on 19th Nov 05 showing 14 of those rear gardens. NB The Straid Rd is the main tourist inland country route between Bushmills and Ballycastle. This has been described in a letter to us (13-12-04) from the Divisional Planning Manager as a "Quality residential development"

If you can shed light on, or add to, any of the above points, then please write or contact us at 32 Eagry Park, or by phone, or by email on : - brian@eagry.com

Thanks

Top
<< Return to first page of Eagry