 In a letter to the Planning Case Office on 7 May 2002 (in response to the second amended plan) we made the following observation:-

7 May 2002
"With the recent unveiling of the "Climate Change Study", a Government funded research document, Northern Ireland Environment Minister Dermot Nesbitt commented that researchers had found there is a low public awareness and concern about climate change and its impact.

Flooding is one of the impacts that we are very aware of, yet we were told when visiting your Planning Department in April that the Planning Service "Has no policy on global warming and flooding" ….. Surely the authorities including the Northern Ireland Planning Service cannot ignore media coverage in recent years of the severe flooding problems elsewhere in the UK?"

 
Acceptance. Here is an extract from the "acceptance" letter written on 18th November 2003 to the Planners by an official of the Rivers Agency
18 Nov. 2003
" 1. A designated watercourse known to us as the Distillery Burn affects the above site and photographic evidence shows that the low-lying parts of the site adjacent to this watercourse are prone to flooding.

2. Rivers Agency advises Planning Service against permitting development in floodplains or the in-filling of floodplains to facilitate development. Consequently development of this site should be restricted to that part of the site, which lies above the 100-year flood level. This is estimated to be 22.67m OD at the downstream end of the site, 23.87m OD at the spillway and 23.90m OD at the upstream end of the site. A suitable freeboard is normally added to this level for design purposes. The site layout plan (Drg. No. 02/55:02) submitted to Planning Service on 28 May 2003 would therefore be acceptable. (This emphasis of the sentence was on the original Rivers letter)

3. It should be noted that (the) .......Distillery extracts water from the Distillery Burn and any outfalls from the development should be downstream of the extraction point at the spillway."

"Freeboard" mentioned in the above letter, is an extra area on the flood plain boundary in addition to the recommended "No Build and no Infill" area. This freeboard enlarges the sloping sides of the 100 year flood level. A member of the Rivers Agency Operations Support Unit defined 'freeboard' as :- "A technical term, and in this context, it is the vertical distance or height above a design level to allow for fluctuations in the water surface caused by, for example, wave action."
 
A 100 year flood plain (referred to as Q100) is a "prophesy" by the Rivers Agency which has defined an area they calculate will flood at least once in a hundred years. It could flood more often than that but once in a hundred years is enough to merit being put in that category. The Rivers Agency even included a large-scale plan of the development area with the flood plain marked in blue. This plan is available for you to see here at No. 32
 

On 10 Feb 2004 we visited the Area Engineer for the Rivers Agency and took with us the May 2003 cross section plans of the proposed developments which accompanied the "acceptable" drawing 02/55:02 and the Engineer was able to calculate for us just how much encroachment there was into the 100 year flood plain. It appears the Chartered Engineers for the Developer are proposing to raise the ground in that flooding area by about 2 metres, and to build the road on top of that. Parts of some of the houses will also be on the edge of this flooding area. Is the technical jargon for this operation .. "in-filling of floodplains to facilitate development". ? (See letter above in white box)

 
For copyright reasons I can't show you any plans or layouts, so have taken information from several of them to come up with these cross sections to give you an idea of the amount of infilling proposed. Infilling which has been accepted by Rivers Agency. Infilling across valuable wetland.

Here is a scaled cross section of the site at the end nearest the caravan site. I have drawn it in flood. The arrow marks the 23.9 OD. You will note in the above letter that development should be restricted to that part of the site which lies above that level. i.e. nothing between the arrow and the stream. Wee blob on the left is a shepherd with a sheep for scale. Yes I know they are standing in water but I was running out of paper on that side! The stream in normal conditions lies in the dip below the shepherd.

Now follows the same scaled cross section but this time showing the extent of the proposed infilling and the position of one of the houses. That's a wall at the top of the embankment near the stream, presumably to stop vehicles falling into the flood water. And the dip between the wall and the house is a road.

 

And here's another cross section. Still in the upper field but this time nearer the Straid Road. Once again a scale-drawing of the site in flood with the same shepherd and again the arrow marks the boundary of the 100 year flood plain and which, according to the letter to the Planners, the Rivers Agency say there should be no infilling or building between that arrow and the stream.

Now follows the same scaled area but this time showing the proposed infilling and building.

 
And our Rivers Agency engineer also calculated for us that this artificial embankment (May 2003 Plan) would encroach in one place over 28m into this flooding area, coming within 4 metres of the stream bank. (In a subsequent letter to us (15/4/04) the Director of Operations, Rivers Agency, describes the above infilling as "small" and "insignificant") The same engineer explained flood water, squeezed into a smaller area by in-filling, would back-up upstream.
During our visit, the engineer was also able to confirm our suspicions that the May 2003 Site Layout Plan ( Drg 02/55:02) submitted to the Planners, would put parts of numbers 46, 47, 48 and 49 all within the flood plain area defined by the Rivers Agency.
 
We wrote (16/2/04) to the Chief Executive of the Rivers Agency asking him why their policy on building and in-filling on a flood plain is not put into practice ending with the following observation:-

16/2/2004
"Our conversation on 10th Feb 2003 with .... (the Area Engineer), pointed up the differences between the stated principles/stance of Rivers Agency and what is actually acceptable. Interesting in this case, with the calculations he made for us during our meeting, one can actually see, mathematically, by how much Rivers Agency sticks to their principles".

We have now had a reply. This is on a separate page and I suggest you read on down to the bottom of this page before clicking for the Rivers Agency reply (Yes I know it's a shambles trying to find your way around this web site but so many elements are intertwined.)


So Rivers Agency say no infilling or development should take place within the Q100 area which they define very precisely, then in the same paragraph accepts infilling and development within that very same proscribed area. So we queried this contradiction with the Divisional Planning Manager who replied ...

13 Dec.2004 
" This was an informative and “people buying a dwelling and their solicitors will wish to satisfy themselves that the prescribed levels have been adhered to”.
DIVISIONAL PLANNING MANAGER

So there we have it. It's not the fault of the Planners who approve plans which allow development on a flood plain, but it's up to solicitors to satisfy themselves that "levels have been adhered to"

 
Some background information. Whilst talking on the phone (7/5/02) to a member of the Rivers Agency we were told that if a developer goes ahead and builds in a flood plain the Rivers Agency cannot stop them, only advise. Surely the law needs to be changed to rectify this

Maintenance. The Rivers Agency also recommend several "Planning Informatives" should be included in any planning decisions including this one :-
"Where a Designated Watercourse flows through or adjacent to a development site, it is considered essential that a working strip of minimum width 5m is left along the bank in order to facilitate future maintenance of the watercourse by the Rivers Agency. Actual requirement should be determined in consultation with the Agency."