| FLOODING AND INFILLING. A letter from the Director of
Operations - Rivers Agency. |
On 16/2/04, we wrote to the Rivers Agency asking why their
policy on building and in-filling on a flood plain is not put into practice?
We quoted back to them their own letter ( 18 Nov 03) in which they say "......development
of this site should be restricted to that part of the site, which lies
above
the 100-year flood level." Yet in the same paragraph in
the same letter announce that ".....The
site layout plan ……submitted to Planning Service on 28 May
2003 would therefore be acceptable." That's the plan which
shows considerable infilling and portions of dwellings also within the
100 year flood plain
area. We also asked for a copy of the Agency's document
defining their policy
for the
protection
of
flood
plains.
We received a reply from the Rivers Agency Director of Operations on
9/3/04. Here are some extracts from his letter: - |
9/3/04
".......As requested I have enclosed
a copy of "Policy and Practice
for the Protection of Floodplains in Relation to Development" which
was published on 26 March 2002 which is after the date of the original
Planning Applications above in July 2001."
|
|
| Now I wonder why the writer of this letter found it worth mentioning
that the
Agency's
Policy
document
came
out after the
original planning application? Is he
inferring that the policy does
not apply to this proposal, even though it wasn't until a radically altered,
May 2003 plan, was proposed that the Agency signalled its acceptance? (a
year
after
this
policy document was published). We have had a reply which appears
at the bottom of this page. I have put extracts of this Rivers Agency
policy
document on this site. You can
find
details
at the
bottom
of this
page. |
| |
| The Director of Operation's letter continued : - |
"The Rivers Agency, as the
Drainage Authority for Northern Ireland and in this capacity, advises
Planning Service on the drainage aspects of any proposed development.
Planning Service may, or may not accept this advice in granting
Planning Permission; although they would usually take Rivers Agency's
advice with very few expectations (sic)
In relation to the above applications
the amount of encroachment of the infilling into the floodplain
on the southern bank is approximately 25% in area terms. However,
the Agency must also consider local pondage both upstream and
on a northern bank. If these areas are taken into account the encroachment
in area terms is reduced to 10% or less. In addition the run-off
from the development will be collected and discharged downstream
of the existing road culvert. Therefore, the overall effect of
water entering the system upstream of the existing road culvert
will be very similar to the present system." |
|
| |
| In our letter we pointed out that ..."Parts of the proposed dwellings
and a road were also shown to be on this artificial embankment on the flood
plain." The reply was : - |
"The drawing which
Rivers Agency found acceptable is the drawing dated 28 May 2003.
On the
basis of a fax to the developer's agent dated 14 November 2003
Rivers Agency confirmed that this was the final layout drawing.
The lowest floor levels on this drawing are 25.80 m which is 1.90
metres above Q100 level. This ensures that none of the properties
are flooded unless the Q100 levels were to be dramatically exceeded;
which is very unlikely." (hey, no-one's told us this is
the final layout drawing! Subsequently we wrote to the Divisional
Planning Manager asking just which is the final approved plan,
to be told [7/4/04] that this May 2003 version was the approved
plan. But this version has not been publicised. See "Differs" section
on front page) |
|
| But we were not referring to the height of of these dwellings above
the Q100 mark but the position of these buildings.
i.e. partly on the 100 year floodplain. |
| |
| The Director of Operations then went on to say : - |
| The drawing dated 5 November
2003, which shows more infilling, is a copy of an original proposal
which was found
unacceptable. This was submitted to Planning Service merely to agree
finishes such as colour of roof tiles, which is why Planning Service
did not forward it to ourselves for comment. I would emphasise that
the drawing dated 28 May 2003 is the final layout drawing. |
|
| Now this is where things get even more confusing. First of all the 5th
November 2003 plan is patently NOT A COPY of an original proposal. There
are less houses shown, and several differences in house types. But ignoring
that, it would appear several agencies refer to the drawing dated 28th
May 2003 as the "final layout". This drawing is the "Private
Streets Determination" which shows different information from
the July 2002 layout, which was the last one published in the Press as
an amended plan. The May 2003 now turns out to be the final approved
plan. (see "Differs" section on front page.) |
| And here is the final part of the letter :- |
"Regarding
your point about double standards I do not believe that such have
been applied.
Whilst the Agency's aims is to advise against permitting development
in floodplains each site is examined on its individual merits and
cognisance taken if the development will have "significant" impact
downstream. In this case the impact was deemed to be insignificant.
Indeed I would point out if
Rivers Agency did not advise Planning Service it is possible that
the original layout which included much more infilling may well
have received approval.
I am content that in this
case the main objectives of the floodplain policy have been adhered
to and that the development will not exacerbate flooding elsewhere.
I trust that this response
allays your concerns". |
|
| "Each site is examined on its individual merits" I
cannot see a more individual investigation than to stipulate the actual
area of this particular site - i.e "22.67m
OD at the downstream end of the site, 23.87m OD at the spillway .... " etc
etc. |
|
| We replied (22 March 04) thanking
the man for his detailed explanation of why they had accepted the infilling
and again asked the simple question:- .
"Why
in that letter to Planners did Rivers Agency say - 'thou shalt not
infill' yet in that very same paragraph say- 'but you can in this case'?" Here
is his reply (15 April 2004) |
15/4/04
"Development is being
restricted to levels which lie above the levels quoted although I
agree this
includes the small
area of infilling which as I explained in my previous letter (See
above original letter) was deemed to be insignificant". My
addition in italics |
|
| We also asked why he thought it necessary to give the date of publication
for the "Policy" document. The Director of Operations replied as follows:- |
15/04/04
My reasons for quoting the date of publication
of the "Policy
and Practice for the Protection of Floodplains" in relation to
Development were twofold. Firstly to flag up that this policy has only
recently been formalised, and secondly, to show that this policy could
not have been rigidly applied to the first planning application in
respect of this site as policy cannot be applied retrospectively.
However our staff were applying the principles in effect and by
doing so they were using "existing custom and practice".
Of course, 1 am not saying
that the Agency does not need to be guided, or needs to abide by
the policy but as I explained in my previous
letter (See above original letter) each site is examined on
its own merits.
|
|
CLICK HERE to read extracts
from the Rivers Agency Circular -
"Policy
and Practice for the Protection of Floodplains in Relation to Development"
to
see how the advice given in this March 2002 document matches up
to, or flies in the face of, the action taken by the Agency, when accepting
a plan submitted a year later in May 2003 |