RIVERS AGENCY POLICY AND PRACTICE FOR THE PROTECTION OF FLOODPLAINS
IN RELATION TO DEVELOPMENT. Pub. DARD 26 March 2002 |
| "Direct Powers and Responsibilities of
Rivers Agency It is important to note that Rivers Agency has no direct statutory control over development but can and where appropriate will seek to influence planning matters through advice and comment in relation to Development Plans. Planning Consultations and through its advice to developers. " |
"Planning Service and Development Planning The protection of floodplains from the physical threats posed by development is heavily dependent on the powers exercised by the Department of the Environment. Planning Service. The Planning Service is responsible for protecting the flood defence interests of people whose property may be affected by development proposals. However, Rivers Agency is a statutory consultee of Planning Service with respect to Development Plans, individual sites and aspects of development control. The Agency's role is to advise Planning Service on the implications of development proposals on drainage and flood defence issues. The floodplain policies detailed in this document apply to the Agency's response to both Development Plans and to individual Planning consultations. In the Planning Service document 'A Planning Strategy for Rural Northern
Ireland' Policy PSU 10 states that development will not generally be permitted
in areas known to be at serious risk from flooding, coastal erosion or land
instability. It also states that there will be a general presumption against
development, including raising, of land, where such development would be
likely to increase the risk of flooding elsewhere. |
| "Policy Statements The following Rivers Agency Policy statements reflect the general approach that will normally be taken by Rivers Agency. It is recognised however, that exceptional circumstances may arise. For clarity the various elements of the overall Floodplain Policy have been stated as 7 No. sub-policy (There then follows seven statements. Here are two of them. ) Policy FP2 Rivers Agency will seek to prevent development in areas that are at risk from flooding. Comment Rivers Agency will seek to persuade Planning Service through the Development Plan process and then via individual Planning Consultations, to guide development away from areas which are liable to flood. As far as is practicable, Rivers Agency will advise Planning Service on the degree of flood risk and will seek to ensure, that residential, commercial and industrial development does not take place in areas of high flood risk. If Planning Service decides that, despite the risk from flooding, development in such an area should be permitted for other overriding reasons, Rivers Agency will provide advice to Planning Service on the appropriate standards of any flood protection or mitigation measures. Such works may include flood defences or measures to restore floodplain or provide adequate storage and flood flow capacity. It should be noted that high flood risk areas may still be suitable for certain types of development which does not include building e.g. recreation, sport, amenity and conservation uses. Policy FP3 Rivers Agency will seek to restrict development that would directly or indirectly increase the risk of flooding to other properties. Comment New development can directly affect the flood risk or have an impact on the drainage of nearby land. The owners of such land would have, an expectation that they should be protected from any adverse effects resulting from development. The impact of a single development may be small
and difficult to quantify accurately but cumulative effects of further
development will eventually
reach measurable proportions, development is not properly controlled,
there will be a cumulative detrimental effect. Therefore, through the
Development Plan process and via consultations on individual developments,
Rivers Agency will advise Planning Service against such development where
there are likely to be increased risks of flooding to other properties." |
| "New Development
Where there is an overriding case for development in a floodplain. then mitigation measures need to be taken to protect new development and existing property. These may include the following where appropriate:-
|
"Planning Service, should be advised that total
protection from flooding cannot be guaranteed and development within
a flood prone area will inevitably
remain at some risk from flooding. |